Time and Work-Aptitude Questions and Answers Discussion Page For Q Id 554c6394889c8371286

Interview Questions and Answers

A completes 40% of a work in 8 days. If B is 60% as efficient as A, find the time taken by complete the rest of the work.

A  

20 days

B  

18 days

C  

30 days

D  

24 days


Correct Option - A

Explaination

Time taken by A to complete 60% of the work

= 8*60/40

= 12 days

B is 60% as efficient as A

Time taken by B to complete 60% of the work

= 12*100/60

= 20 days